Prince2 Practitioner Sample exam questions

Want to assess your knowledge on the PRINCE2 project management method? Attempt these Practitioner Certification exam questions. Please note these questions are sample practitioner questions (based on the 2009 versions of PRINCE2) and should not be mistaken for 'live' exam questions.

Many more sample questions plus Practitioner Sample Exam papers are included as part of our comprehensive training material.

Visit here for sample PRINCE2 Foundation Sample Questions

The sample questions listed below demonstrate the various question style formats within the PRINCE2 Practitioner Exam.

Classical Multiple Choice

The customer's quality expectations are first defined in the:

1. End Stage Report
2. Project Product Description
3. Initiation Stage Plan
4. Quality Register

Yes/No Questions

Column 1 is a list of true and false statements about when a Highlight Report is created. For each of the statements in column 1 select either A (Yes, this correct) or B (No, this is incorrect)

Column 1 Column 2
1. When reviewing the stage end A (Yes, this correct)
2. At project closure B (No, this is incorrect)
3. During a stage  
4. When issuing a Work Package  

Multiple Responses

  Identify which two of the following are true
1. The project mandate is created by corporate management
2. The project manager is responsible for delivering benefits
3. The project manager may act as project assurance
4. Project board is responsible for project assurance

Matching

Column 1 contains statements about various project situations. Column 2 lists four PRINCE2 management products. Select from column 2 the management product in which the statement from column 1 should be recorded. Each selection from column 2 can be used once, more than once or not at all.

  Column 1 Column 2
1. The implementation of the project's product will increase the organization's ongoing operational costs A. Business Case
2. Stage costs are projected to increase by 3 per cent however this stage is projected to be completed within cost tolerances B. Risk Register
3. The designs identified a major requirements problem, this issue has now been resolved C. Stage Plan
4. The requirements must remain unchanged for this stage to succeed D. Highlight Report

Sequencing

The Chief Executive has requested a major change to the product brochure. This change will impact project tolerances. Identify the order in which the following activities should occur.

1. Escalate this issue to the next level of management
2. Examine the issue
3. Implement the Exception Plan
4. Record the issue in the Issue Register
5. Create an Exception Plan.

a) 4, 2, 1, 5, 3
b) 4, 2, 5, 3, 1
c) 2, 4, 1, 5, 3
d) 2, 4, 1, 3, 5
e) 4, 1, 2, 5, 3

Assertion and Reason

Lines 1 to 3 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Selection Assertion Reason  
A. True True AND the reason explains the assertion
B. True True BUT the reason does not explain the assertion
C. True False  
D. False True  
e. False False  

  Assertion   Reason
1. The Highlight Report should be immediately updated if a new issue has been identified Because Team members require updates on every project issue on a regular basis
2. Team Managers should create Highlight Reports Because Highlight Reports are created on a periodic basis throughout a stage
3. Work Packages are authorized by Team Managers Because Team Managers are responsible for creating the Team Plan to control the team's work

 

The above questions are copyright of HiLogic Sdn Bhd 2009 and should not be copied without the written permission of HiLogic Sdn Bhd.

Visit here for sample PRINCE2 Foundation Sample Questions

Quick Links

  • Upcoming Training
  • PRINCE2 - Kuala Lumpur
    Foundation: 21 - 23 May
  • PRINCE2 - Kuala Lumpur
    Practitioner: 24 - 25 May
  • P3O - Kuala Lumpur
    Foundation: 10 - 12 July
  • PRINCE2 - Kuala Lumpur
    Foundation: 16 - 18 July
  • PRINCE2 - Kuala Lumpur
    Practitioner: 19 - 20 July